403 US Hyperscale Data Centers Use Up to 99 TWh of Electricity Annually
- Nicole Kobie
- 345 views
A Harvard study estimates 403 large US data centers use 68–99 TWh of electricity and produce 25.7 million metric tons of CO₂, with fossil fuels supplying much of their power.

The 403 US hyperscale data centers examined in a Harvard study consume as much electricity as some states and produce an estimated 25.7 million metric tons of carbon dioxide each year. The findings put a facility level figure on the power demand of some of the largest computing sites, while showing how strongly their emissions depend on where they draw electricity.
Researchers with the Harvard Data Science Initiative calculated that the facilities used between 68 and 99 terawatt hours of electricity, depending on their operating levels. That range is roughly 1.8% of annual US electricity consumption. The researchers also compared the demand with that of Indiana, Michigan and Tennessee, and reported that it exceeded Denmark’s annual electricity use.
The study, which examined electricity use and related emissions over a year, appeared in Nature Sustainability. Its estimate of 25.7 million metric tons of carbon dioxide is two to three times higher than estimates from 2018.
Scale and scope of the estimate
The numbers apply to hyperscale data centers, a subset of the US data center estate. The researchers counted 403 sites, while the country has around 5,000 data center facilities in total. The study therefore offers a detailed view of a large, energy intensive group, but it is not a measurement of every facility operating in the country.
That distinction matters for operators and infrastructure planners comparing the findings with local demand. The study’s electricity range reflects different levels of facility activity, so it should be read as a span rather than as one fixed figure. Its emissions estimate also represents the electricity associated with the sites, not a full accounting of every environmental effect linked to building or operating them.
Lead author Gianluca Guidi, a postdoctoral fellow in Harvard’s Department of Biostatistics, said facility level information on environmental effects has been limited while data center construction and power decisions are underway. He described the analysis as an effort to fill that information gap.
Fossil fuels supply much of the power
The researchers estimated that fossil fuels supplied about 54% of the electricity generation associated with these hyperscale facilities. Gas accounted for 38% and coal for 15%, with the mix varying significantly by region. Those percentages help explain why the same amount of electricity demand can carry different emissions depending on the regional power system serving a site.
Grid access is another operational pressure. Data center operators have turned to gas power amid difficulties obtaining electricity from grids, a shift that can affect the emissions profile of new capacity. For IT teams assessing expansion plans, the study points to power sourcing and location as factors that shape the environmental footprint alongside the size and workload of a facility.
The researchers’ figures cover activity only through April 2025. Guidi said new facilities have been built and existing campuses expanded since then, while demand for AI computing has continued to grow. The study is therefore a snapshot of a fast changing sector, and its estimates may not describe the current total in 2026.
What the study does and doesn’t measure
The analysis focused on electricity consumption and corresponding carbon dioxide emissions. It did not measure health outcomes or other pollutants. Francesca Dominici, the corresponding author and director of the Harvard Data Science Initiative, described two possible health pathways: climate effects associated with carbon dioxide, and pollutants released by fossil fuel power plants serving regional electricity demand.
Dominici named fine particulate matter, nitrogen oxides and sulfur dioxide as pollutants linked to heart and lung disease and premature death. Her comments concern the effects associated with fossil fuel power generation; the study itself did not quantify those health impacts or determine how many people may be affected.
That separation is useful when interpreting the results. The electricity and emissions estimates provide a basis for understanding the scale of power demand, while questions about local pollution exposure require additional evidence. People living near or downwind of power plants may face effects even when they live far from the data center drawing on that regional supply, Dominici said.
For operators, the practical takeaway is to track both projected electricity demand and the source of that power when evaluating site and capacity decisions. The Harvard study supplies a new benchmark for 403 large US facilities, but its coverage and April 2025 cutoff limit how directly it can describe the full data center estate today. Continued construction and expanding AI workloads make updated facility level measurements important for understanding how quickly demand and emissions are changing.